Rangeview Heights Mixed Use Development Project – Subcontract for Civil Works
Brief description of the works: Sub Contractor
Project consists of bulk and detailed earthworks, access road construction, storm water and drainage, residential and industrial subdivision – services. The project requires detailed earthworks with different pad levels, rock anchors and retaining walls to be constructed to major cut areas and full subdivision services to be installed.
Amount of contract: 18 Million Kina
Name of Employer: Lamana Development Limited
Award Date: 29 June 2018 Completion Date: May 2019
Completed Projects
Port Moresby International Airport (PMIA) Asphalt Overlay Works
Brief description of the works: Prime Contractor Works includes profiling/milling of existing asphalt surfaces, manufacture and place 32,000ton of asphalt to airport specification, RESA area reconstruction, main runway and taxiway overlay and general purpose apron reconstruction and reseal.
Amount of contract: 68 Million Kina Name of Employer: National Airports Corporation (NAC) Award Date: 27 November 2017 Completion Date: 30 October 2018
Port Moresby Sewerage Upgrade Project
Brief description of the works: Sub Contractor Works consist of detailed bulk earthworks, access road construction, stone pitch and gabion slope stabilization, trenching, bedding backfill and trunk main sewer laying. Over 270, 000 man hours to date, +130,000m3 bulk earthworks (cut to fill/spoil).
Amount of contract: 80 Million Kina Name of Employer: Dai Nippon Construction Award Date: 18 November 2015 Completion Date: 7 November 2018
Reconstruction of Independence Drive
Brief description of the works: Prime Contractor Works includes construction and upgrading of existing road to 4 lane divided road, drainage upgrade underground utilities, water reticulation system, telecommunication, electrical and road furniture and associated works including construction of 6 lane access road to the Parliament house in Port Moresby.
Amount of contract: 18 Million Kina Name of Employer: National Capital District Commission (NCDC) Award Date: July 2018 Completion Date: October 2018
Design and Construction of Sir Reuben Taureka Highway
Brief description of the works: Prime Contractor The project was a design and construction of 11.4 km of 4 lane, dual carriageway with 5 roundabouts, bridge, culverts, stone pitched and rock lined drainage, medium strips, kerbs, bus bays and street lighting.
The project was completed in 15 months with over 1 million man hours worked, over 310,000 tons of earthworks, 220,000 tons of road base placed and 178,000m2 of prime seal and asphalt.
Amount of contract: 167 Million Kina Name of Employer: National Capital District Commission (NCDC) Award Date: 5 July 2015 Completion Date: 30 April 2017
Design and Construction of Morea Tobo Road (6 Mile to 7 Mile) and Associated Roads
Brief description of the works: Prime Contractor Works includes upgrading of existing roads to 4 dual lane consist of bulk earthworks, pavement works, storm water drainages, culverts, bus bays, street lightings, seal and asphalt works.
Amount of contract: 63 Million Kina
Name of Employer: National Capital District Commission (NCDC)Award Date: 31 May 2013 Completion Date: May 2015
ExxonMobil Permanent Facilities Compound
Works consist of bulk earthworks and site preparation including slope/scour protection, side drain construction, asphalt and concrete pavement.
Amount of contract: 40 Million Kina
Name of employer: Exxon Mobil PNG & Leighton/CPB Contractors